Term | Session | Sitting | Sector | Ministry | Qn No | Date |
---|---|---|---|---|---|---|
2015-2020 | Session 7 | Sitting 14 | Energy and Minerals | Wizara ya Nishat | 112 | 2017-04-28 |
Name
Victor Kilasile Mwambalaswa
Sex
Male
Party
CCM
Constituent
Lupa
Primary Question
MHE. VICTOR K. MWAMBALASWA aliuliza:-
Je, ni lini Serikali itapeleka umeme kwenye Kata za Ifumbo, Lualaje, Mafyeko na Kambikatoto katika Wilaya ya Chunya?
Name
Dr. Medard Matogolo Kalemani
Sex
Male
Party
CCM
Constituent
Chato
Answer
NAIBU WAZIRI WA NISHATI NA MADINI alijibu:-
Mheshimiwa Naibu Spika, kwa niaba ya Waziri wa Nishati na Madini, napenda kujibu swali la Mheshimiwa Victor Kilasile Mwambalaswa, Mbunge wa Lupa, kama ifuatavyo:-
Mheshimiwa Spika, utekelezaji wa Mradi Kabambe wa Usambazaji Umeme Vijijini Awamu ya Tatu umeanza rasmi nchi nzima tangu mwezi Machi, 2017. Mradi huu utajumuisha vipengele-mradi vitatu vya densification, grid extension pamoja na off grid renewable ambapo inalenga kuongeza wingi wa usambazaji umeme kwenye vijiji ambavyo vimefikiwa na umeme lakini kwenye vitongoji havijaunganishwa. Kata za Ifumbo, Kambikatoto, Lualaje na Mafyeko zimejumuishwa katika mradi wa REA Awamu ya Tatu wa grid extension ambao utaanza na kukamilika mwaka 2020/2021.
Mheshimiwa Naibu Spika, kazi ya kupeleka umeme katika kata hizo itajumuisha ujenzi wa njia ya umeme wa msongo wa kilovoti 33 yenye urefu wa kilometa 20, ujenzi wa njia ya umeme ya msongo ya kilovoti 0.4 yenye urefu wa kilometa 76, ufungaji wa transfoma kumi pamoja na kuwaunganishia umeme wateja wa awali 1,145. Gharama ya kazi hii ni shilingi bilioni 3.142.